Uvas Road Pavement Rehabilitation

Uvas Road Pavement Rehabilitation From Little Uvas Road to Watsonville Road, Federal Project Number: STPL 5937(219)

Project Description

The project will rehabilitate Uvas Road.  Work will include pavement repair, crack sealing, hot mix asphalt (HMA) overlay, shoulder backing, adjust existing manholes and monuments to new grade, thermoplastic pavement striping & markings, roadside signs and delineators. Uvas Road was selected for rehabilitation due to relatively low Pavement Condition Index (PCI) in the low 60s.

Project Status

  • ​Project advertisement: March 24, 2020. 
  • Bid opening: April 23, 2020.
  • Bid award:  June 2, 2020.
  • Pre-construction meeting: July 22, 2020.
  • Notice to Proceed: July 27, 2020.
  • Construction schedule:  From 08/17/2020 To 10/26/2020.

    Construction Update: 10/28/2020

    Construction Activities

    Schedule

    All Construction Activities

    ​Completed 

    Final Inspection

    Oct 21, 2020, Completed

Funding

  • ​Federal Surface Transportation Program One Bay Area Grant (STP OBAG),
  • Vehicle Registration Fee Valley Transit Authority (VRF-VTA), 
  • Measure B (2016)
  • County Road Fund

Project Location

Located in the City of Morgan Hill at County maintained Uvas Road between Little Uvas Rd and Watsonville Rd.

Project Map of Uvas Road Pavement Rehabilitation

​​​​​Related Documents

©2021 County of Santa Clara. All rights reserved.