Storm-Damaged Roads

last update: 03/15/2023 - 10:19

2023 Storm-Damaged Roads 

The Roads and Airports Department is working as quickly as possible to permanently repair roads that were damaged during the storms in December and January. Damage was concentrated in the Santa Cruz Mountains and San Antonio Valley east of Mount Hamilton. All roads damaged by the storms have been partially reopened. Roads staff will update this webpage regularly to keep residents informed of the status of repairs. 

The County Office of Communications and Public Affairs produced a video about the work Roads personnel did to protect the community during this winter’s storms

Mines-Road

Mines Road:  Repair Status 

On Feb. 7, the contractor started work at the first location on Mines Road.  On Feb. 17, the contractor completed installation of the new culvert pipe, including placement of base rock cover, and metal plates. These metal plates allow for one lane of travel through the site until final paving can be completed.  Completing the paving depends on weather conditions - successful asphalt placement requires dry and relatively warm weather.  Final paving has been delayed due to cold, wet weather. It is anticipated that paving will be completed by the end of March.

The same contractor is scheduled to work on repairs at the second location on Mines Road, which is currently open with one lane of travel.  New culvert pipe has been ordered.  However, delivery is expected to take four to five weeks, due to supply chain issues.  When the contractor receives the pipe, they will re-mobilize, and repair work will commence.  This work will necessitate a four-to-five-day full road closure.  We will provide as much notice as possible of this closure and keep it to an absolute minimum. 

2023 Storm Repair Projects 

No. Road Name
(alphabetical)
Description of Damage Proposed Repair Repair
Status
Road Status* Construction Schedule
1 Bear Creek Road Site 1 Road Undermined
Failed Culvert
Replace culvert,
install downstream junction box/manhole
replace debris rack
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control.  TBD
2 Bear Creek Road Site 2 Sink hole Replace culvert
reconstruct road section
Pre-construction Road currently subject to one lane closure with stop traffic control.  TBD
3 Bear Creek Road Site 3 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control.  TBD
4 Black Road Site 1 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control.  TBD
5 Calaveras Rd Site 1 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
6 Mines Road Site 1 Road washed out Replace culvert
Reconstruct road section
Construction Road currently open to one lane traffic.
EFFECTIVE FRIDAY 2/17; 5 pm.
4/1 - Final Paving Completed
 Weather dependant 
7 Mines Road Site 2 Slipout Replace culvert
Reconstruct road section
Pre-construction Road currently subject to one lane closure with stop traffic control ~ 4-5 Weeks for material delivery (new culvert).
Followed by repair work.  Construction will take 4 to 5 days requiring full road closure.
8 Old Santa Cruz Hwy Site 1 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
9 Old Santa Cruz Hwy Site 2 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
10 Old Santa Cruz Hwy Site 3 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
11 San Antonio Valley Road Site 1 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
12 San Antonio Valley Road Site 2 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD
13 San Antonio Valley Road Site 3 Slipout Install Micropiles
construct retaining wall
reconstruct road section
Design Road currently subject to one lane closure with stop traffic control TBD

*The list below does not include emergency work or closure due to work performed by utility companies.  

©2023 County of Santa Clara. All rights reserved.