Storm-Damaged Roads

last update: 02/02/2024 - 11:04

2023 Storm-Damaged Roads 

The Roads and Airports Department is working as quickly as possible to permanently repair roads that were damaged during a series of winter storms from December through March.  Damage was concentrated in the Santa Cruz Mountains and San Antonio Valley east of Mount Hamilton.  Roads staff is updating this webpage regularly to keep residents informed of the status of repairs. 

The County Office of Communications and Public Affairs produced a video about the work Roads personnel did to protect the community during the 2022-23 winter storms.

Monthly Board Memos

Additional Schedule Considerations
Some road repair locations that involve the conveyance of water through pipes or the construction within natural drainage swales are experiencing schedule impacts due to resource agency permitting processing. Permits are required from the U.S. Army Corps of Engineers, Fish and Wildlife, and the Regional Water Quality Control Board. The requirements for conducting environmental assessments, ascertaining potential ecological concerns, and mitigating any adverse effects may add delay to some permanent repair projects. The project team is actively working with the resources agencies and expert consultants to ensure compliance with all permitting requirements while finding efficient ways to expedite the restoration of the roads through temporary measures if necessary. 

2023 Storm Damage Repair Projects 

Links in the road name column will direct to location-specific pages with additional information. Some pages are still under development and will become available in the near future. 

*The list below does not include emergency work or closure due to work performed by utility companies

 

 

 

 

 

 

 

 

 

 

Clayton Road Closure

 

 

 

San Antonio Valley Storm Damage map

 

 

 

No. Road Name
(alphabetical)
Description of Damage Proposed Repair Repair
Status
Road Status Construction Schedule
1 Aldercroft Heights Road Site 1 Landslide To be determined following geotechnical evaluation Pre-Design Road open to traffic. Geotechnical field work complete.  Final report has been received and is being reviewed.
2 Aldercroft Heights Road Site 2 Slipout TBD Evaluation Road open to traffic. TBD
3 Alma Bridge Road Partially failed culvert and slope erosion Replace culvert
Reconstruct road section
Evaluation Road open to traffic. TBD
4 Bear Creek Road Site 1 Road Undermined
Failed Culvert
Replace culvert,
install downstream junction box/manhole
replace debris rack
reconstruct road section
Substantially Complete Road open to traffic. Roadway construction substantially complete.  Related closeout activities are ongoing.
5 Bear Creek Road Site 2 Sink hole Replace culvert,
reconstruct road section
Evaluation Road currently subject to one lane closure with stop traffic control TBD
6 Bear Creek Road Site 3 Slipout Construct retaining wall, restore road Evaluation Road currently subject to one lane closure with stop traffic control TBD
7 Black Road Site 1 Slipout Stabilize slope with shotcrete and soil nails, restore road Substantially Complete Road open to traffic. Roadway construction substantially complete. Related closeout activities are ongoing.
8 Calaveras Road Site 1 Slipout Replace culvert, stabilize slope Evaluation Road open to traffic. TBD
9 Clayton Road Landslide Construct retaining wall, restore road Pre-Design Temporary gravel access has been re-established subject to one-lane stop control Permanent repair TBD.
10 Hicks Road Site 1 Slipout TBD Evaluation Road currently subject to one lane closure with stop traffic control TBD
11 Hicks Road Site 2 Slipout TBD Evaluation Road open to traffic. TBD
12 Hicks Road Site 3 Slipout TBD Evaluation Road open to traffic. TBD
13 Kincaid Road Site 1 Uphill landslide Clear remaining landslide debris Complete Road open to traffic. Work complete.
14 Kincaid Road Site 2 Slipout TBD Evaluation Road currently subject to one lane closure with stop traffic control TBD
15 Mines Road Site 1 Road washed out Replace culvert
Reconstruct road section
Substantially Complete Road open to traffic. Roadway construction substantially complete.  Related closeout activities are ongoing.
16 Mines Road Site 2 Culvert failure Replace culvert
Reconstruct road section
Substantially Complete Road open to traffic. Roadway construction substantially complete.  Related closeout activities are ongoing.
17 Mines Road Site 3 Slipout TBD Evaluation Road open to traffic. TBD
18 Montebello Road Shoulder erosion TBD Evaluation Road open to traffic. TBD
19 Mount Madonna Road Slipout TBD Evaluation Road currently subject to one lane closure with stop traffic control TBD
20 Old Santa Cruz Highway Site 1 Road Slipout
Failed Culvert
Construct retaining wall, replace culvert, restore road Evaluation Full Road Closure. Site to be winterized to minimize further damage.
21 Old Santa Cruz Highway Site 2 Slipout Stabilize slope with shotcrete and soil nails, restore road Substantially Complete Road open to traffic Roadway construction substantially complete. Related closeout activities are ongoing. 
22 Old Santa Cruz Highway Site 3 Slipout TBD Evaluation Road open to traffic. TBD
23 Old Santa Cruz Highway Site 4 Shoulder slipout TBD Evaluation Road open to traffic. TBD
24 On Orbit Drive Slipout TBD Evaluation Road open to traffic. TBD
25 Quimby Road Roadway settling TBD Evaluation Road open to traffic. TBD
26 San Antonio Valley Road Site 1 Slipout Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road Construction On-going Road currently subject to one lane closure with stop traffic control Substantial completion targeted early 2024
27 San Antonio Valley Road Site 2 Slipout Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road Pre-construction Road currently subject to one lane closure with stop traffic control Late 2023/Early 2024
28 San Antonio Valley Road Site 3 Slipout Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road Construction On-going Road currently subject to one lane closure with traffic signal control Substantial completion targeted December 2023
29 San Antonio Valley Road Site 4 Slipout Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road Design Road currently subject to one lane closure with stop traffic control Early 2024
30 San Antonio Valley Road Site 5 Slipout Stabilize slope with shotcrete and soil nails, construct retaining wall, restore road Design Road currently subject to one lane closure with stop traffic control Early 2024
31 Weller Road Culvert failure Replace culvert Evaluation Road open to traffic. TBD
32 West Road Slope erosion Stabilize slope with shotcrete and soil nails Substantially Complete Road open to traffic. Roadway construction substantially complete.  Related closeout activities are ongoing.
33 Willow Springs Rd Undermining Rebuild embankment, restore roadway Evaluation Road open to traffic. TBD

For updates on County roads closures, visit the Road Closure webpage.