Page Mill Road Intersection Improvement at Hanover Street
last update: 05/02/2022 - 08:52
County Notice of Street Resurfacing for Page Mill Road Intersection at Hanover Street to California Avenue and 530-feet east of the intersection.
Planned Dates: 5/14/2022 to 5/15/2022 (pending weather)
Hours: 7:00 a.m. to 4:00 p.m. (Day work - Saturday and Sunday)
Project Limits:
Intersection of Page Mill Road and Hanover Street in Palo Alto.
Project Description:
The project will provide operational and safety improvements at the intersection of Page Mill Road and Hanover Street. Work will include:
• Providing a second westbound left turn lane on Page Mill Road
• Modifying the traffic signal which will include re-phasing, installing new poles, and upgrading pedestrian push buttons to make them contactless and accessible for the blind
• Upgrading existing pedestrian curb ramps to comply with current Americans with Disability Act (ADA) standards
• Installing improvements for bicyclists
• Installing signing and striping modifications
• Installing civil modifications to the south-west corner to accommodate vehicular turning movement
Project Timeline:
Estimated Construction Schedule: Mid-October 2021 to May 2022.
Funding Source(s):
• 2016 Measure B Expressway Program
• City of Palo Alto
Project Location:
Project Document Library:
Signed Project Plan Set - Page Mill Road Intersection Improvements at Hanover Street
Point of Contact Regarding This Project:
Email: [email protected]