Lawrence Expressway Pavement Rehabilitation Project

Project Description:
This project has limits between Quito Road and Homestead Road.  The project will repair failed pavement areas and resurface the expressway with a microsurface overlay, construct new Americans with Disabilities Act (ADA) compliant ramps, retrofit pedestrian ramps, repair curb and gutter, install new traffic loops,  and restripe the expressway within project limits.

Construction Update - 12/8/17: Project striping has begun and is expected to take about 2 weeks.

Schedule of Construction: August 2017 through November 2018 .
The first charge day is August 9, 2017.     Contract duration 70 working days.

  • Removal and replacement of asphalt concrete; ongoing.  Completion by 9/29/17.
  • Removal and replacement of concrete; ongoing.  Completion 10/30/17.
  • Extruded concrete curb; ongoing.   Completion 10/13/17.

Bid Opening:  June 1, 2017 at 2:00 p.m.

Project Award:  Graham Contractors.

Project Engineer: Paul Pascoal (408) 573-2485