Lawrence Expressway Pavement Rehabilitation

Last updated:06/22/2021 - 13:14

Project Description

The project will rehabilitate Almaden Expressway from Blossom Hill Road to Harry Road.  Work will include: pavement repair; hot mix asphalt (HMA) overlay; repair of sidewalk, driveway approach, and curb & gutter; upgrade of existing ramps to comply with current American Disability Acts (ADA) standards; adjustment of existing manholes/monuments/utilities to new grade; installation of new inductive loops for vehicles and bicycles; installation of new battery back-up cabinet and system; placement of thermoplastic pavement striping, markings and roadside signs.

Project Status - Project Completed

  • Project advertisement:  June 23, 2020.

  • Bid opening: July 16, 2020.

  • Bid award: August 11, 2020.

  • Pre-construction Meeting: September 24, 2020.

  • Notice to Proceed: November 2, 2020.

  • Construction schedule: From Nov 2, 2020 to May 2021.  Project Completed. 

    NOTE: Schedule subject to change due to weather and unforeseen circumstances. 

Funding

  • Measure B (2016)
  • County Road Fund

Project Location

Located in the City of San Jose at County maintained Almaden Expressway between Blossom Hill Road and Harry Road.