  • Almaden Expy Pavement Rehabilitation From Blossom Hill Road To Harry Road

Almaden Expy Pavement Rehabilitation From Blossom Hill Road to Harry Road

Project Description

The project will rehabilitate Almaden Expressway from Blossom Hill Road to Harry Road.  Work will include: pavement repair; hot mix asphalt (HMA) overlay; repair of sidewalk, driveway approach, and curb & gutter; upgrade of existing ramps to comply with current American Disability Acts (ADA) standards; adjustment of existing manholes/monuments/utilities to new grade; installation of new inductive loops for vehicles and bicycles; installation of new battery back-up cabinet and system; placement of thermoplastic pavement striping, markings and roadside signs.

Project Status

  • Project advertisement:  June 23, 2020.
  • Bid opening: July 16, 2020.
  • Bid award: August 11, 2020.
  • Pre-construction Meeting: September 24, 2020.
  • Notice to Proceed: November 2, 2020.
  • Construction schedule: From Nov 2, 2020 to March 16, 2021

Construction Update:  1/25/2021

Construction Activities:

Schedule

Pre-paving Construction – Electrical & Concrete

Completed

 

  PCC Extruded Curbs

  PCC Curb & Gutter/Sidewalks/Driveways

  Ramps & Domes

  Electrical Lead Time

  Remove & Salvage Battery Back-up Cabinets

  Install Alpha Battery Back-up Cabinet & System

  Install Cameras

Paving Construction

Suspended work due to weather from 1/19/2021 through 1/29/2021.

  Wedge Cut

  Base Repairs

  2” Full Mill

  Lower Utilities (CIR – Manholes & Monuments)

  Lower DHs

  Striping Removal

  CIR

  Electrical Loops

  County Review for Layout

  2” Overlay

  Cat-track

  Raise DHs

  Raise Utilities

  County Review for Cat-tracks

  Final Striping & Signs

Funding

  • Measure B (2016)
  • County Road Fund

Project Location

Located in the City of San Jose at County maintained Almaden Expressway between Blossom Hill Road and Harry Road.