Almaden Expy Pavement Rehabilitation From Blossom Hill Road to Harry Road
Project Description
The project will rehabilitate Almaden Expressway from Blossom Hill Road to Harry Road. Work will include: pavement repair; hot mix asphalt (HMA) overlay; repair of sidewalk, driveway approach, and curb & gutter; upgrade of existing ramps to comply with current American Disability Acts (ADA) standards; adjustment of existing manholes/monuments/utilities to new grade; installation of new inductive loops for vehicles and bicycles; installation of new battery back-up cabinet and system; placement of thermoplastic pavement striping, markings and roadside signs.
Project Status
- Project advertisement: June 23, 2020.
- Bid opening: July 16, 2020.
- Bid award: August 11, 2020.
- Pre-construction Meeting: September 24, 2020.
- Notice to Proceed: November 2, 2020.
- Construction schedule: From Nov 2, 2020 to March 16, 2021
Construction Update: 1/25/2021 |
|
---|---|
Construction Activities: |
Schedule |
Pre-paving Construction – Electrical & Concrete |
Completed
|
PCC Extruded Curbs |
|
PCC Curb & Gutter/Sidewalks/Driveways |
|
Ramps & Domes |
|
Electrical Lead Time |
|
Remove & Salvage Battery Back-up Cabinets |
|
Install Alpha Battery Back-up Cabinet & System |
|
Install Cameras |
|
Paving Construction |
Suspended work due to weather from 1/19/2021 through 1/29/2021. |
Wedge Cut |
|
Base Repairs |
|
2” Full Mill |
|
Lower Utilities (CIR – Manholes & Monuments) |
|
Lower DHs |
|
Striping Removal |
|
CIR |
|
Electrical Loops |
|
County Review for Layout |
|
2” Overlay |
|
Cat-track |
|
Raise DHs |
|
Raise Utilities |
|
County Review for Cat-tracks |
|
Final Striping & Signs |
Funding
- Measure B (2016)
- County Road Fund
Project Location
Located in the City of San Jose at County maintained Almaden Expressway between Blossom Hill Road and Harry Road.